Municipography is a summary of current issues going through the Raleigh City Council and other municipal departments in the city. The point is to try to deliver any video, photos, and text associated with the discussions happening at City Hall or elsewhere. Since this is a downtown Raleigh blog, the focus is on the center of the city.

Email readers, this post contains embedded video which you may not see in your inbox. I recommend jumping to the blog to see all the content.

Last week at the Raleigh City Council meeting, a few projects we’ve discussed on the blog were presented and discussed. The council approved the sale of the city-owned lot on Salisbury Street, known as “Site 4”, to Summit Hospitality Group, Ltd who plans to build a hotel. The plans for the new Capital Boulevard bridge over Peace Street were also discussed as construction on that project is planned for Summer 2016. Finally, an update on the 2030 Comprehensive Plan was given by the planning department.

Residence Inn on Salisbury Street

See Raleigh City Council – 2-18-14 – City of Raleigh and Summit Hospitality Group on YouTube.

In short, the council approved the sale of Site 4 to Summit Hospitality Group, Ltd to build a Residence Inn hotel. This sale was recommended by the Budget and Economic Development Committee last month and now makes it final.

From the city’s press release:

Following a Feb. 18 Public Hearing, the Raleigh City Council approved the sale of .52 acres on South Salisbury Street, between South Street and Lenoir Street, to Raleigh-based Summit Hospitality Group, Ltd. Approval of the $1.73 million deal will result in the construction of an 11-story Marriott Residence Inn with 140 to 154 additional rooms within walking distance of the Raleigh Convention Center. The site is also known as Site 4 and is considered to be “one of the most important infill sites within the Convention and Cultural District” in the City’s South End Master Plan.

*Sale of Downtown Site Approved

For more details on this project, jump to a recent post with all the details.

Capital Boulevard Bridge

See Raleigh City Council – 2-18-14 – NCDOT Capital Boulevard Bridge Replacement Projects on YouTube.

The Capital Boulevard bridge over Peace Street is slated for replacement in the next few years and designs have been in the works for quite awhile. The latest on this topic is covered in good detail in the post linked below, including some excellent conversation by readers.

Between the “base” alternative (cheaper) and the “enhanced” alternative (costlier) this is where the city has to step up. There is strong public support for the enhanced alternative but the feds only have enough money for the base alternative.

According to the presentation, in May 2014 an alternative will be chosen with construction planned for Summer of 2016.

From the city’s press release:

Each bridge is proposed for replacement under the Federal Highway Administration’s bridge replacement program. City staff has coordinated the replacement of these bridges with NCDOT to be consistent with the City’s adopted Capital Boulevard Corridor Plan. In each case, NCDOT has developed base alternatives that rebuild each interchange following the existing configuration, and enhanced alternatives that more closely follow the City’s corridor plan recommendations. In order to pursue the enhanced alternatives at either location, the City would be required to pay for the difference in cost above each base alternative.

*Council Reviews Alternatives for Capital Boulevard Bridge Replacement Projects

2030 Comprehensive Plan Update

See Raleigh City Council – 2-28-14 – 2030 Comprehensive Plan – January 2014 Progress Report on YouTube.

The 2014 Progress Report was presented to council and can be found on the city’s website. Some highlights from the presentation:

  • Our city’s comprehensive plan continues to be a national model for city planning.
  • Updates are meant to keep the plan up-to-date with emerging trends and any city restructuring.
  • Of the total 465 action items since adoption, 61 have been completed and now removed, 275 are in progress and 50 have still not been started.

The newest emerging trends that city staff will be studying are:

  • Community Resiliency – planning for extreme weather and emergencies and how the city continues to be responsive and can recover.
  • Innovation Districts – how to foster new growth nodes around unique ideas and innovation.
  • Autonomous Vehicles – how to plan for the upcoming use of self-driving cars and taxis.
  • Sharing Economy – services like bike share, car share, self-rental properties are a future trend. Examples include Airbnb, ZipCar, and B-Cycle.

Similar Posts:

Comments

Comments are disabled here. That's because we're all hanging out on the DTRaleigh Community, an online forum for passionate fans of the Oak City.

8 Comments

  1. To me it’s shocking that the betterments at Wade Avenue would cost $15 million over the base alternative. No wonder the city is going to just let them go with the base option there considering the minimal benefits. I like what Eric Lamb says (paraphrasing): “If I had $15 million to spend near Capital and Wade, I would extend West Street.”

  2. Good news on the Hotel, though it’s years overdue. We really need to step up the hotel room supply around downtown soon.

  3. I agree. Time for Raleigh to step up. The enhanced versions will be worthy investments and quality examples for future projects.

  4. The new renders of the hotel look much better. Not as good as the Lafayette which we lost from that site, but still a structure with much more character than the CC Marriott.

  5. Raleigh Really needs to take it up a notch and Build more high rise Offices and Hotels in the Downtown Area. You really need more Hotels in the area, Go pass 7 stories and build 15 to 20 story Hotels and Offices.

  6. @mark: We don’t have the developers to make it happen. Highwoods is currently the only one that could build tall, but they are still not as committed to downtown. They want, but they can’t… Not yet. Not until the city leaders begin to lure major employers into our CBD. Not easy, but then again it is just as tough for other cities.