With planning going back to 2013, the first phase of the makeover for the Blount and Person Street duo should be starting soon. Design work for Phase 1 of the corridor has been completed and last I heard, the construction bids are out now.

The project can be summed up according to this excerpt from a City Manager’s Weekly Report:

The design of the Phase I Implementation of the Blount Street – Person Street Corridor Study is complete. The project will reconfigure pavement markings and install a continuous bike lane on both streets from Hoke Street to Old Louisburg Road. North of Edenton Street, the streets will be resurfaced and curb ramps will be upgraded. The design of the project will reconfigure Blount Street and Person Street to both have two consistent lanes of standard width. It will also reconfigure Wake Forest Road as a three-lane avenue, with one travel lane in each direction, a center turn lane, and bike lanes.

That’s a pretty nice and lengthy bike lane as Hoke to Old Louisburg is almost three miles. Bonus that both streets are getting a lane which offers long rides in each direction.

The project should wrap up by the end of the year and then start moving on towards more aspects of the Blount Street – Person Street Corridor Plan.

We’re tracking this and other bike lanes on the DTRaleigh community. Join the conversation.

Similar Posts:

Comments

Comments are disabled here. That's because we're all hanging out on the DTRaleigh Community, an online forum for passionate fans of the Oak City.